Downstream Reference List 2007
| Client |
Project |
Description of Activity |
|
|
| 2006
| Client |
Project |
Description of Activity |
CJSC «Ryazanskaya NPK», Ryazan |
ÀVT-3, ÀÒ-6, waste liquid incinerator, waste liquid incinerator facilities, 30/4, 29/3, ÒÊ-1, AVT-2, tank 69/4 units
L-35/6-300, LG-35/8-300B units |
Development of the Detailed Design of «Connecting of open relief loads from safety valve to flare system».
Development of the Detailed Design of «Connecting of open relief loads from safety valve to flare system». |
| «RBS-Holding» LTD |
ELOU-AVT-3 unit CJSC «Ryazanskaya NPK» |
Implementation of Feasibility Study and principle process and assembling solutions concerning updating options of ELOU-AVT-3 unit or new construction. |
| CJSC «Lisichianskaya oil investment company» |
ÀVT-8, L-35-11/1000 #1 units |
Heat and hydraulic calculations of Ê-3,4 columns as one split at ÀVT-8 unit, calculations of K-1, K-2 of L-35-11/1000 #1 unit – column of gasoline segregation of catalytic cracking Ñ5 - 215°Ñ and steaming section of hydrofined naphtha cracking. |
«PO «KINEF» LTD, Kirishi |
Bitumen Units 19/6 and 19/10 at «PO «KINEF» LTD |
Development of the Detailed Design of replacing reciprocating air compressors with screw air compressors for Bitumen Units 19/6 and 19/10. |
NPK company «Petro-service» LTD, Moscow |
ELOU-AVT-8 #2 unit at CJSC «LINIK» |
Detailed Design: «Replacement of vacuum-creating system of ELOU-AVT-8 #2 unit at CJSC «LINIK» |
CJSC «PIRO», Moscow |
LCh-35-11/600 unit at «PO «KINEF» LTD
24/7 unit at «PO «KINEF» LTD |
Development of Detailed Documentation concerning re-tie in of new Ê-601 column of LCh-35-11/600 unit at «PO «KINEF» LTD
Development of Detailed Documentation concerning re-tie in of new Ê-1 of 24/7 unit at «PO «KINEF» LTD |
CJSC «Ryazanskaya NPK», Ryazan |
ELOU-AVT-4 unit at CJSC «RNPK» |
Implementation of ELOU-AVT-4 unit updating scheme (Scheme of heat and material calculations, including heat exchange diagram)
Development of Detailed Documentation concerning ELOU-AVT-4 unit updating scheme | 2005
| Client |
Project |
Description of Activity |
| JSC «Stroitelno-Inzhenernaya Kompaniya» (SINKO) Moscow |
|
Development of the Detailed Design for Customization of Typical Design of the Package Plant for Non-Woven Material Production |
JSC «Naftaros» Moscow |
ELOU-AT-7 Unit at Turkmenbashinsky Refinery
ELOU-AT Units 2, 6, 7 at Turkmenbashinsky Refinery |
Development of the Detailed Design for ELOU-AT-7 Unit with the Annual Capacity of 3.0M t ELOU-AT-7 Unit at Turkmenbashinsky Refinery
Development of the Detailed Design for Local and Recycling Water Supply for ELOU-AT Units 2, 6, and 7 at Turkmenbashinsky Refinery |
JSC «PIRO» Moscow |
ELOU-AVT-2 Unit at JSC «PO KINEF» |
Development of the Detailed Design for the New Piping of the New Equipment (K-3 and K-4 Columns) of ELOU-AVT-2 Unit at JSC «PO KINEF» |
JSC «Tumen Neftyanaya Kompaniya» Tumen |
|
Services for Operating Strategic Planning Model and Optimization of Client’s Assets Utilization in Crude and Petroleum Product Distribution, and for Operating Aspen DPOTM Business Planning Models |
JSC «VosokGazProm» Tomsk |
Hydrocarbon Processing Units at JSC «VosokGazProm» |
Development of Investment Justification for Construction of Hydrocarbon Processing Units at JSC «VosokGazProm» in (four) different regions |
JSC «PO KINEF» city of Kirishi |
Units 19/6 and 19/10 at JSC «PO KINEF» |
Development of Detailed Design Documents for Replacing Pipeline Electrical Heating with Steam Heating for Bitumen Units 19/6 and 19/10 at JSC «PO KirishNefteOrgSintez» |
| JSC «NefteMash» Moscow |
Flare Facility at JSC «NK «Rosneft – TNPZ» |
Designer’s Supervision and Engineering Support of the Facility Construction in accordance with Detailed Design of the Flare Facility at JSC «NK «Rosneft – TNPZ» (city of Tuapse, Russia) |
JSC “PetroKhim Engineering» Moscow |
Izomerization Unit at JSC «ANKhK»
Hydro-cracking Unit GK-3 at JSC «ANKhK» Refinery |
Development of the Baseline Design of Izomerization Process for Izomerization Unit at JSC «ANKhK». Phase 1.
Development of the Baseline Design for Upgrading Crude Unit Blocks of Hydro-cracking Unit GK-3 at JSC «ANKhK» Refinery |
| JSC «KhimMashExport» Moscow |
|
Feasibility Assessment (TER) for a Test-bed for Full Scale Rolling Stock Prototypes. | 2004
| Client |
Project |
Description of Activity |
JSC «NefteKhMash» Moscow |
ÀÒ-1 Atmospheric Unit at JSC «NK Rosneft-TNPZ»
Secondary Gasoline Distillation Unit at JSC «LUKOIL_VNP» |
Designer’s Oversight over the Implementation of Worn-out Equipment of the ÀÒ-1 Atmospheric Unit at JSC «NK Rosneft-TNPZ» and Technical Support of the Unit Overhaul during Preparation and Implementation Phases
Development of the Detailed Design for Overhauling Secondary Gasoline Distillation Unit #7 (22/5 type) in Shop #3 at JSC «LUKOIL_VNP» |
JSC «Ryazan NPK» Ryazan |
|
Development of Two Options for the Feasibility Study of a Synergetic Project «Raising Isomerizate Octane Number and Recovery of the High Concentration Isopentane Fraction» |
| JSC «LUKOIL- RostovNefteKhimProekt» Rostov |
ELOU-AVT Unit at JSC «LUKOIL-ONPZ» |
Development of the Customized Detailed Design for the Installation of the P-101/1,2 Furnace and Transfer Lines of the Ê-2 and Ê-3 columns of ELOU-AVT Unit at JSC «LUKOIL-ONPZ».
Designer’s Oversight over the Construction and Installation under the Customized Detailed Design for the Installation of the P-101/1,2 Furnace and Transfer Lines of the Ê-2 and Ê-3 columns of ELOU-AVT Unit at JSC «LUKOIL-ONPZ». |
JSC «TNK-BP Management» Moscow |
|
Consulting Services for Planning and Optimization of Client’s Assets Utilization in Crude and Petroleum Product Distribution including data reconciliation verification (Items 1.1, 1.2, 1,3 of the Agreement). Development of a Computer Model for Strategic Planning of Assets Utilization in Crude and Petroleum Product Distribution to Functional Design Specification. Technical Consulting Services in using DPO System for Client’s specialists. |
| JSC «PetroKhim Engineering» Moscow |
AUTN-2 Unit at the JSC «SibNeft-Omsk NPZ» |
Development of the Detailed Design for an Automated Three-Track On-Spot R/R Cistern Loading Station (AUTN-2) at TSB-2 of the JSC «SibNeft-Omsk NPZ» - Process Design, Instrumentation Design, Process Automation Design (in the scope required for the delivery of «Marcon Ingenieurgesellschaft mbH» under Design #2.733) to ensure meeting the requirement of Item 4.1 of SNiP 11-01-95. |
| JSC «SlavNeft-Yaroslavl NOS» Yaroslavl |
AVT-2 Unit at JSC «SlavNeft-Yaroslavl NOS» |
Development of the Detailed Design for «AVT-2 Unit Transfer Piping Vibration Elimination» |
| JSC «KhimMashExport» Moscow |
Ethylene Oxide Plant at JSC «NizhnekamskNefte-Khim» |
Development of the Detailed Design for Replacement of Heat Recovery Exchanges at Ethylene Oxide Plant at JSC «NizhnekamskNefteKhim» |
| JSC «LUKOIL-Inform» Moscow |
|
Development of the Pilot (Typical) Design on the Basis of Modern DBMS Solutions for the On-line Simulation and Monitoring of Process Efficiency at Company’s Refineries |
| JSC «Kirishinefteorgsintez» in the city of Kirishi |
ELOU-AVT-2 Unit at JSC «Kirishinefteorgsintez» |
Development of the Detailed Design for Retrofitting ELOU-AVT-2 Unit |
| JSC «NPO Neftekhimiya», Moscow |
Hydrogen Production Unit |
Developing Process Diagram for the Hydrogen Production Unit |
OAO «MNPZ», Moscow |
ELOU-AVT-6 Unit at OAO «MNPZ» |
Detailed Design Development for advanced gasoline fractions separation process at ELOU-AVT-6 Unit. |
ZAO «PIRO» Moscow |
Ê-7 Tower of Gas Fractioning Unit at OOO «PO Kirishinefteorgsintez» |
Detailed Design Development for replacing Ò-16 re-boiler at K-7 tower of Gas Fractioning Unit at OOO «PO Kirishinefteorgsintez» |
2003
| Client |
Project |
Description of Activity |
| OOO "National Fuel and Energy Company" Moscow |
AT Atmospheric Unit for Processing Gas Condensate at Tula Refinery |
Base Design Development for Refurbishment of AT Atmospheric Unit for Processing Gas Condensate at Tula Refinery. Phase I. Principal Process Solutions. |
ZAO "RNPK" Ryazan |
ELOU-AVT-6 Unit |
Detailed Design Development for Distribution Control System for ELOU-AVT-6 Unit |
OAO "KATAMAK" Moscow |
Transfer Lines of Ê-2, Ê-3 Towers of ELOU-AVT Unit at OAO "LUKOIL-ONPZ" |
Preliminary Design Development for the replacement and configuration change of Transfer Lines of Ê-2, Ê-3 Towers of ELOU-AVT Unit at OAO "LUKOIL-ONPZ" |
| ZAO "NAFTAROS", Moscow |
ELOU-AT-6 at "Turkmenbashi NPZ” |
Development of the Detailed Design for ELOU-AT-6 Plant, Capacity 2.5 mln. t/year at “Turkmenbashi NPZ” |
| ZAO "NAFTAROS", Moscow |
ELOU-AT-4 TNPZ |
Development of the Base Design for Reconstructing ELOU-AT-4 Plant at “Turkmenbashi NPZ” |
| ZAO "Gornorudnaya Kompaniya «RANOVA»", Moscow |
Alcohol and TBA Recovery |
Development of the Detailed Design for Alcohol and TBA (Acetylene Tetra-bromide) Recovery Plant at the Quartz Production and Process Facility in Lipetsk oblast |
ZAO "NefteKhimProekt", St. Petersburg |
UK-231 Tower of Hydro Cracking Plant OAO "Slavneft-YaroslavNefteorgSyntez" |
Modification of the Detailed Design for the Vacuum System of the UK-231 Tower of Hydro Cracking Plant at OAO "Slavneft-YaroslavNefteorgSyntez" |
| OAO "Syzran NPZ" |
ELOU-AVT-6 OAO "Syzran NPZ" |
Heat Transfer Optimization for ELOU-AVT-6 Plant |
| OAO "KhersonNeftepererabotka", Kherson |
ELOU-AVT-2 OAO "Kherson-Neftepererabotka" |
Development of Process Flow Diagram and Design Criteria for the Design of Contacting Devices of Rectification Towers of ELOU-AVT-2 Plant at OAO "KhersonNeftepererabotka" |
ZAO "Petrochim Engineering", Moscow |
Gas Fractioning Unit for Catalytic Cracking Plant, “OAO KNPZ” |
Heat and Hydraulic Analysis of Thermal Syphon Boilers, Item 402-Ò08, 402-Ò09 for Gas Fractioning Unit for Catalytic Cracking Plant at “OAO KNPZ” |
ZAO "Petrochim Engineering", Moscow |
Orthoparaxylol Plant |
Modification of Installation Drawings for "Ï-101” Furnace Piping of Orthoparaxylol Plant |
OOO "NPKTs Inzhneftemash", Moscow |
|
Development of the Software System for the Analysis of «Fire-Heater»Heating Furnaces |
2002
| Client |
Project |
Description of Activity |
OAO "Lengiproneftekhim", St. Petersburg |
ELOU-AVT-2 and ELOU-AVT-1 at JSC "PO Kirishi-nefteorgisintez" |
Improving Performance of ELOU-AVT-2and ELOU-AVT-1. Phase 1. Development of the Detailed Design for Retrofitting and Re-piping of Vacuum Tower Ê-5 of ELOU-AVT-2 of Shop #1 at JSC "PO Kirishi-nefteorgisintez" |
AOZT "Neftekhimproekt", St. Petersburg |
Tower UK-231 of Hydrocracking Plant, JSC “Slavneft-Yaroslav-nefteorgsyntez” |
Development of the Detailed Design for the Vacuum System for Tower UK-231 of Hydrocracking Plant, JSC “Slavneft-Yaroslavnefteorgsyntez” |
ZAO "PIRO", Moscow |
Pre-Hydrotreating Unit of LCh -35-11/1000 Plant |
Development of the Detailed Design for Equipping the Initial Hydro Treatment Unit of LCh -35-11/1000 Plant with Corrosion and Salt Deposits Control Assemblies for Low-temperature Equipment |
| OOO "NEFTEKHMASH", Moscow |
Cogeneration Plant at OAO "NK Rosneft-TNPZ" |
Development of the Detailed Design for the Fuel Gas Preparation Unit for Process Furnaces and Cogeneration Plant Boilers at OAO "NK Rosneft-Tuapse Refinery" |
| OOO "NEFTEKHMASH", Moscow |
Refinery Flare System at OAO "NK Rosneft-TNPZ" |
Development of the Detailed Design for the Reconstruction of Refinery Flare System at OAO "NK Rosneft-TNPZ" |
OAO "Slavneft-Yaroslav-nefteorgsintez", Yaroslavl |
Transfer Lines of Towers Ê-1à and Ê-2 of AVT-3 Plant |
Development of the Detailed Design for the Replacement and Reconfiguration of the Transfer Lines of Towers Ê-1à and Ê-2 of AVT-3 Plant |
OOO "NPK Kedr-89", Moscow |
|
Development, Customization, and Implementation of "SAFETY" and "TOKSI" Systems for the Assessment of Emergency Consequences |
2001
| Client |
Project |
Description of Activity |
JSC " Ryazansky NPZ" Ryazan |
ELOU-AVT-4 JSC “Ryazan Refinery” |
Contractor Design development for ELOU-AVT-4 JSC “RNPZ” Plant upgrade to increase light oil and vacuum distillates output as well as their quality improvement |
JSC "Naftaros" Moscow |
ELOU-AT-2 Turkmenbashinsky Refinery |
Contractor design development for ELOU-AT-2 Unit upgrade at Turkmenbashinsky Refinery |
| JSC "Petrochim Engineering" Moscow |
Sulfur Production Plant, JSC "Kirishinefte –orgsintez" |
Contractor design development for Sulfur Production Plant upgrade at JSC “Kirishinefteorgsintez” |
JSC "Neftekhmash", Moscow |
ÀÒ-1 JSC "RosNeft - Tuapse Refinery" |
Development of Detailed Design for the Replacement of Worn-out Equipment of AT-1 Crude Unit at JSC ”RosNeft - Tuapse Refinery” |
JSC "Neftekhmash" Moscow |
AT-6 , JSC "Ryazan Refinery" |
Process calculations for gasoline secondary distillation unit of AT-6 Plant at Ryazansky Refinery |
JSC "NITs NK LUKOIL", Moscow |
|
Development of a Data Base for Expert/Analytical Evaluation of Design Solutions for Reconstruction of Petro-Chemical and Refinery Facilities. |
JSC "BIS Ltd." Rostov-on-Don |
JSC "LUKOIL-Rostov-neftechimproject" |
Software delivery & adjustment for departments of JSC "LUKOIL-Rostovneftechimproject" |
2000
| Client |
Project |
Description of Activity |
| ZAO "Petrokhim Engineering", Moscow |
Plants 19/6 and 19/10 of Shop #2 at OOO "PO Kirishi-NefteOrgSintez" |
Detailed Design for the reconstruction of Bitumen Plants 19/6 and 19/10 of Shop #2 at OOO "PO Kirishi-NefteOrgSintez" |
JSC "Khabarovsky Refinery" Khabarovsk |
AT, JSC "Khabarovsky Refinery" |
Technology Schedule development for the product production on AT Plant. |
JSC "Khabarovsky Refinery" Khabarovsk |
AT, JSC "Khabarovsky Refinery" |
Development of the Technical Upgrade Project of AT Plant at JSC" Khabarovsky Refinery" |
JSC "PIRO" Moscow |
G-43-107 |
Technical documentation development for pentane fraction removal from K-304 stabilizer of G-43-107 Plant as raw material for TAME production. |
JSC "PIRO", Moscow |
G-43-107 |
Production forms and records development for connecting 4th section of P-102 furnace in parallel to P-101 furnace of G-43-107 Plant |
TsNII after A. Krylov academician (central research and design institute) St. Petersburg |
Oil and Gas condensate Refinery Plant |
Technical and technology solutions preparation for technical specification development for design of Oil and Gas condensate Refinery Plants 100000 tones annual capacity calculated for raw material taking into account their positioning on floating base. |
| JSC “Yugansky Refinery” Yugansk, Khanty-Mansiysky Autonomous Region |
Oil Refinery Plant 500000 tones capacity |
Investment substantiation development for Oil Refinery Plant 500000 tones capacity construction near Yugansk, Khanty-Mansiysky Autonomous Region |
JSC “Ecodest-O” Orenburg |
Plant for organic and polymer waste recycling |
Primary data development for design and contractor design project for organic and polymer waste recycling Plant |
JSC “Ecodest-O” Orenburg |
Plant for organic and polymer waste recycling |
Technical project development for design of primary data development for organic and polymer waste recycling Plant |
| JSC “ TNK” |
Bitumen production at Lysychansky Refinery |
Technical and Economical Proposals development for construction the Bitumen production at Lysychansky Refinery |
JSC NTF“Bis Ltd” Rostov-on-Don |
JSC “LUKOIL-Rostov-neftechimproekt” |
Pre-project inspection and Project development of CAD JSC “ LUKOIL- Rostovneftechimproekt” |
| TUP “PO Northern Machinery Building Enterprise” Severodvinsk |
MLSP “Prirazlomnaya” |
Consulting services for Technical and Economical Proposals preparation to equip upper buildings of MLSP “Prirazlomnaya” |
1999
| Client |
Project |
Description of Activity |
| JSC “Slavneft – Yaroslavnefteorgsintez” Yaroslavl |
Elementary Sulfur Plant |
Contractor design and Technical project development for Elementary Sulfur Plant control system. |
| JSC "PO Kirishinefteorgsintez" |
ELOU-AVT-6 Plant JSC "PO Kirishi-nefteorgsintez |
Development of work package to equip ELOU-AVT-6 Plant with Distributed Control System and to improve process technology |
JSC "PIRO" Moscow |
GFU Plant JSC "PO Kirishi-nefteorgsintez" |
Development of detail engineering documentation for overhaul of refrigerating facilities of GFU Plant K-1 Column for JSC "PO Kirishinefteorgsintez" |
| JSC "TNK" |
Crude Stabilization Plant JSC "Stabilization" NNPO Nizhnevartovsk |
Development of Process Specification for engineering, and detail engineering package for revamp of Crude Stabilization Plant JSC "Stabilization" NNPO Nizhne-vartovsk to increase capacity up to 2 MMt/yr in terms of feedstock, and output of gasoline up to 300 thousand t/yr/ |
Volgogradsky Branch "Neftezavodmontazh" Volgograd |
|
Technical supervision of Crude Stabilizing Unit Revamp Project for NNPO, Nizhnevartovsk |
"RIFIN", Ltd. Moscow |
|
Strength calcucations for transfer line of Vicebreaking Unit |
JSC "Giprovostokneft" Samara |
|
Adaptation and supply of CAD system for JSC "Giprovostokneft" |
1998
| Client |
Project |
Description of Activity |
GP “Techmashcomplex” Moscow |
ELOU AVT-7 Plant JSC "TAIF-NK" |
Development of detail engineering for refurbishment and revamp of ELOU AVT-7 Plant Vacuum Unit at JSC "TAIF-NK", Nizhnekamsk |
GP “Techmashcomplex” Moscow |
ELOU AVT-7 Plant JSC "TAIF-NK" |
Development of basic and detail engineering documentation, manufacture and delivery of internals as revamp of K-10 Column of ELOU-AVT-7 Plant, JSC "TAIF-NK". |
JSC "Ryazan Refinery" Ryazan |
AT-6 Plant, JSC "Ryazan Refinery" |
Basic Engineering for naphta and gas condensate processing facilities involving K-4 Column of AT-6 Plant, JSC "Ryazan Refinery" |
JSC "Ryazan Refinery" Ryazan |
AVT-1 and AVT-2 Plants, JSC "Ryazan Refinery" |
Development of detail engineering for revamp of vacuum units of AVT-1 and AVT-2 Plants to produce narrow lube cuts from topped crude supplied from AT-6 Plant, JSC "Ryazan Refinery" |
| JSC "TAAS-YURIAKH Neft" |
20,000 t/yr Bitumen Unit |
Engineering of 20,000 t/yr Bitumen Unit aimed at changing raw material and meeting the requirements of Inspection Authorities to have the Unit in compliance with applicable codes and regulations |
GP “Techmashcomplex” Moscow |
AVT-7 Nizhnekamsky Petrochemical Complex |
Revamp and refurbishment of AVT-7 Plant Vacuum Unit at Nizhnekamsky Petrochemical Complex. |
JSC CHIMMASHEXPORT Moscow |
Furnace Unit for Korobkovsky GPP |
Development of KM Steel Structures Civil Drawings including Specs for Manufacture and Erection, at the request of KTI SpA (Italy), for Korobkovsky GPP. |
JSC "Ryazan Refinery" Ryazan |
AVT-1 Ryazan Refinery |
Cost Analysis for AVT-1 Unit revamp. |
JSC “NPCEO" Moscow |
AVT Unit Moscow Refinery |
Development of detail engineering to rearrange top pumparound circuit as part of revamping K-10 tower of AVT Unit - JSC Moscow Refinery |
JSC "Trest-Koksochimmontazh" Moscow |
Oil Handling Facilities |
Process calculations and cost evaluation to fulfill the Memorandum on construction of 600 Mt/yr Oil Handling Facilities intended for oil receipt from trunk pipeline, storage and dispatch via rail road. |
TASUR NII AEM Tomsk |
|
Development, adjustment and implementation of integrated CAD system in JSC “TomskNIPINEFT VNK”. |
JV “Key Industry Engineering” Bishkek |
|
Arrangement of development, adjustment and implementation of integrated CAD system. |
1997
| Client |
Project |
Description of Activity |
| JSC Petrochim Engineering Moscow |
AVT-6 Kirishsky Refinery |
Revamp of vacuum system for AVT-6 Unit, Kirishsky Refinery. |
| JSC Petrochim Engineering Moscow |
AVT-6 Kirishsky Refinery |
Outline of design basis and development of detail engineering documents for upgrading K-10 Vacuum Tower, AVT-6 Unit, Kirishsky Refinery. |
JSC "Trest ¹7" Moscow |
|
Development of detail engineering documents for polypropylene silos. |
JSC “NPCEO" Moscow |
ELOU-AVT-6 Moscow Refinery |
Development of detail engineering for emergency discharge of ELOU-AVT-6 Vacuum Unit, Moscow Refinery. |
JSC "Trest-Koksochimmontazh" Moscow |
ELOU-AVT-3 Atirau Refinery |
Development of design documents for replacement of K-2 Tower of ELOU-AVT-3 Unit, Atirau Refinery. |
JSC "Trest-Koksochimmontazh" Moscow |
Mini-Refinery |
Development of detail engineering documents for connecting section of domestic, potable and raw water networks at the site of the Mini-Refinery, Tikhoretsk. |
| Confidential |
|
Development and implementation of the Integrated Information CAD System for JSC “”LUKoil-Rostovneftechimproject”. |
NIK "KEDR-89" Moscow |
ELOU-AVT-3 Komsomolsk on Amur Refinery - Rosneft |
Development of basic engineering package for revamping ELOU - AVT-3 Unit, JSC “Komsomolsk Refinery - Rosneft”. |
JSC "Interchimprom-Oksosintez" Perm |
|
Utility consumption analysis for JSC "Interchimprom-Oksosintez" to reduce production costs. Recommendations on energy saving. |
JSC "NIC NK LUKoil" Moscow |
AVT-3 "LUKoil – Volgogradnefte-pererabotka" |
Analysis and optimization of AVT-3 operating modes, "LUKoil - Volgogradneftepererabotka". | 1996
| Client |
Project |
Description of Activity |
JSC "Karbid" Temirtau |
|
Development of the Feasibility Report for oil refining plant, raw material & commodity product storage facilities at the site of JSC "Karbid". |
JSC "Sunrise" Moscow |
AVT-2 Ryazan Refinery |
Examination of AVT-2 Unit; development of rigorous mathematical model of the Unit; evaluation of operation troubles. Recommendations on Unit upgrade. Outline of design basis for Unit upgrade engineering. |
VNIIKholodmash Moscow |
Refrigeration Plant, JSC “Victoria” |
Revamp of ammonia machine section of the refrigeration plant for JSC “Victoria”. |
JSC "Trest-Koksochimmontazh" Moscow |
Mini-Refinery |
Development of detail engineering documents for sewage water intake facilities. |
| Confidential |
AVT-2 |
Development of detail engineering documents for AVT-2 Unit upgrade and design documents for non-standardized equipment to increase output of products and reduce energy consumption. Conformity of upgraded units of the Plant to codes and standards in effect. |
JSC "Interchimprom-Oksosintez" Perm |
|
Development and approval of engineering documents for production of engine gasoline A-76 and A-92. |
| JSC "LUKoil-Permnefteorgsintez" |
AVT-1, JSC "LUKoil-Permnefteorgsintez" |
Manufacture of Vacu-Pack regular packing set to be installed in the washing section of K-5 Tower, AVT-1 Unit, and technical assistance in erection. |
JSC "Moscow Refinery" Moscow |
G-43-107 Moscow Refinery |
Development of Technical Proposal and Quotation for revamp of G-43-107 Unit gas separation section to the the increase output of propane-propylene fraction to 95%. |
PO "NAFTAN" Novopolotsk, Belarus |
AT-6 PO "NAFTAN" |
Development of Technical Proposal and Quotation for revamp of AT-6 Unit to recover iso-pentane fraction (ON=90) from fraction ibp-62°C. |
PO "Chimprom" Volgograd |
HCI absorption unit |
Recommendations on upgrade of HCI absorption units of Chlor-Methane Plant to reduce energy consumption. |
Joint Venture "MINIOIL" Moscow |
300,000 t/yr Refinery Tikhoretsk |
Development of detail civil engineering for 300,000 t/yr Refinery Project, Tikhoretsk. |
Joint Venture "MINIOIL" Moscow |
300,000 t/yr Refinery Tikhoretsk |
Development of engineering and design documents for advanced fire furnace to cool flue gas down to 220°C. | 1995
| Client |
Project |
Description of Activities |
JSC "Trest N7", Moscow in cooperation with John Brown, Great Britain |
1A/1M Unit, Ryazan Refinery |
Development of detail engineering for catalytic cracking reaction/recovery facilities of 1A/1M Unit, Ryazan Refinery. |
| JSC Petrochim Engineering Moscow |
|
Development of engineering and design documents for the equipment ordered by CTIP (Italy) for Drogobytch Refinery in compliance with the Specification of the Contract between CTIP and JSC “Chernovitcky Machine-Building Factory”. |
| JSC “Chemical Engineering Company”, Moscow |
Vinylchloride Distillation Unit |
Verification of Vinylchloride Distillation Unit operatiliti at 10 ata. | 1994
| Client |
Project |
Description of Activity |
JSC “LUKOIL-Astrakhanneft” Astrakhan |
Small-Size Refinery (atmospheric pressure) JVC “Beshkul” |
Detail engineering for 5,000 t/yr small-size (atmospheric pressure) refinery for JVC “Beshkul” to produce commodity diesel fuel oil and component of commodity gasoline. |
VNIIGAS Moscow |
Modular Unit |
Engineering packages for LPG desulphurization units to produce elementary sulphur and gas fractionating unit to produce household gas. |
GOSNIIKHLORPROJECT Moscow |
Vinylchloride Recovery and Treatment Unit |
Outline of design basis to develop engineering for vinylchloride recovery and treatment unit for Vinyl-chloride Plant based on acetylene hydrochlorination process. |
| Engineering Company “INKOR” Moscow |
AT and AVT Units |
Outline of design basis to develop engineering for 500,000 t/yr ELOU AT and AVT Units. |
JSC Ryazan Refinery Ryazan |
AVT-3 Unit Ryazan Refinery |
Outline of design basis to develop detail engineering for revamp of AVT-3 unit and recommendations on conformity of AVT-3 unit to codes and standards in effect. |
JSC Ryazan Refinery Ryazan |
AVT-4 Unit Ryazan Refinery |
Detail engineering for revamp of AVT-4 Unit to increase the capacity up to 4 MM t/yr and to produce narrow-cut lube oil fractions of preset quality. Development of engineering and design documents for non-standardized equipment. Conformity of the unit to codes and standards in effect. |
PO "NAFTAN" Novopolotsk, Belarus |
AVT-6, PO "NAFTAN" |
Development of AVT-6 unit model to optimize operating modes, including atmospheric crude oil distillation unit and naphta distillation unit. | 1993
| Client |
Project |
Description of Activity |
JSC "Boguchannaft" Boguchani |
Low-Capacity Refinery |
Detail engineering for 50,000 t/yr refinery. |
JSC "Caustic" Sterlitamak |
Dichlorethane Unit as part of Vinylchloride Plant |
Outline of design basis to develop engineering for dichlorethane unit as part of vinylchloride plant based on high-temperature liquid-phase direct chlorinaton. |
VNIINeftemash Moscow |
AVT-5 Unit |
Development of main process approaches for revamp of AVT-5 Unit at Volgograd Refinery to produce narrow-cut lube oil fractions of preset quality. |
PO "Kirghizneft" Kochkor-Ata, Eirghizia |
Low-Capacity Refinery |
Outline of design basis, detail design, manufacture, supply, erection and commissioning of 100,000 t/yr refinery. |
JSC "Neftechimmash-Engineering, Ltd." Moscow |
220-50 Unit for close-cut oil fractions, PO "NAFTAN" |
Development of recommendations on upgrade of vacuum unit to produce narrow-cut lube oil fractions of preset quality. |
PO "Chimvolokno" Krasnoyarsk |
Sodium Sulphate Crystallization, Dehydration and Drying Unit |
Outline of design basis for revamp of mirabilyte crystallization section of complete sodium sulphate crystallization, dehydration and drying unit |
PO "Chimvolokno" Krasnoyarsk |
VVU20 Unit |
Process calculation of AI2 evaporator integrated into VVU20 Unit to verify unit operation under new conditions. | 1992
| Client |
Project |
Description of Activity |
JSC "Chaika" Uglich |
Solvent Recovery Section |
Development of engineering and design documents for waste acetone disposal unit. |
GIPRONIIMedprom Moscow |
Vitamin Plant, Yoshkar-Ola |
Outline of design basis to develop engineering of solvent recovery units. |
SDE "THERMO" Moscow |
Concentrated Diethylbenzene Recovery Unit |
Optimization of the distillation tower integrated into concentrated diethylbenzene recovery unit to improve commodity product quality. |
PO "Angarsknefteorgsintez", Angarsk |
1060 Distillation Unit |
Outline of design basis to develop engineering for revamp of 1060 distillation unit to involve it in hydrogenate stabilization process for white oil production. |
PO "Angarsknefteorgsintez", Angarsk |
1060 Distillation Unit |
Check design of existing equipment of 1060 distillation unit to involve it in hydrogenate stabilization process for white oil production.
|
PO "Sibvolokno" Krasnoyarsk |
Sodium Sulphate Crystallization, Dehydration and Drying Unit |
Outline of design basis for revamp of mirabilyte crystallization section of complete sodium sulphate crystallization, dehydration and drying unit |
| JSC “Chemical Engineering Company”, Moscow |
Wet Dichlorethane Distillation Unit |
Development of optimum process arrangement for wet dichlorethane distillation in amount of 120,000 t/yr at Dichlorethane Plant based on ethylene oxychlorination process. |
|
|